These PMP flashcards cover look-alike pairs that a scenario can hinge on: contingency vs management reserve, risk vs issue, validate scope vs control quality, three contract types. The rest are the earned value letters and the handful of formulas worth knowing cold.

Exam
PMP
Cards
30
Updated
Oct 13, 2026

01Look-alike terms and formulas

Say the answer out loud, then flip. Both sides are on the page, so nothing loads late.

  1. Card 01

    Contingency reserve

    Money or time for identified risks, the known-unknowns. It sits inside the cost baseline, and the project manager can use it under the plan's rules.

  2. Card 02

    Management reserve

    For risks nobody identified, the unknown-unknowns. Outside the cost baseline but inside the budget; using it needs management approval and a baseline change.

  3. Card 03

    Project budget

    Cost baseline plus management reserve. The baseline already contains the contingency reserve.

  4. Card 04

    Risk vs issue

    A risk is uncertain and still ahead; an issue is already happening. When a risk occurs, run its planned response. An unplanned event gets a workaround and an entry in the issue log.

  5. Card 05

    Control quality

    Checks that deliverables are correct against requirements. An internal step, before the customer sees the work.

  6. Card 06

    Validate scope

    The customer or sponsor formally accepts finished deliverables. On an agile team, acceptance happens at the review, against the definition of done.

  7. Card 07

    Quality assurance vs quality control

    Assurance looks at the process and prevents defects. Control inspects the product and finds them.

  8. Card 08

    Cost of quality

    Conformance costs (prevention and appraisal) against nonconformance costs (internal and external failure).

  9. Card 09

    Fixed-price contract

    The seller carries the cost risk. Fits a scope that is well defined.

  10. Card 10

    Cost-reimbursable contract

    The buyer carries the cost risk. Fits a scope that is still uncertain.

  11. Card 11

    Time and materials contract

    A hybrid of the two, used for staff augmentation and small or unclear scope.

  12. Card 12

    EV, PV, AC

    Earned value: budgeted cost of work actually done. Planned value: budgeted cost of work scheduled. Actual cost: what that work really cost. See earned value management.

  13. Card 13

    CV, cost variance

    EV − AC. Negative means over budget.

  14. Card 14

    SV, schedule variance

    EV − PV. Negative means behind schedule.

  15. Card 15

    CPI, cost performance index

    EV / AC. Below 1 means each dollar spent is buying less than a dollar of planned work.

  16. Card 16

    SPI, schedule performance index

    EV / PV. Below 1 means behind schedule.

  17. Card 17

    EAC if current cost performance continues

    BAC / CPI, where BAC is the budget at completion.

  18. Card 18

    EAC if the remaining work goes to plan

    AC + (BAC − EV). The variance so far is treated as a one-off. The other forecasts are on PMP formulas.

  19. Card 19

    ETC and VAC

    Estimate to complete: EAC − AC. Variance at completion: BAC − EAC; negative means a forecast overrun.

  20. Card 20

    TCPI to finish on budget

    (BAC − EV) / (BAC − AC). Above 1 means the remaining work has to run more efficiently than planned.

  21. Card 21

    PERT (beta) estimate

    (O + 4M + P) / 6, with standard deviation about (P − O) / 6. The triangular version is (O + M + P) / 3.

  22. Card 22

    Communication channels

    n(n − 1) / 2. A team of 10 has 45 channels.

  23. Card 23

    Expected monetary value

    Probability × impact. Threats carry a negative value, opportunities a positive one.

  24. Card 24

    Total float

    LS − ES, or LF − EF. The critical path is the longest path through the network and usually has zero float.

  25. Card 25

    Crashing vs fast-tracking

    Crashing adds resources and costs money. Fast-tracking overlaps activities and adds risk.

  26. Card 26

    Tuckman's ladder

    Forming, storming, norming, performing, adjourning. A scenario names the behavior; you name the stage and the project manager's next move. See Tuckman's ladder.

  27. Card 27

    Sprint review vs retrospective

    The review inspects the product with stakeholders. The retrospective is the team inspecting how it works.

  28. Card 28

    Lessons learned vs retrospective

    Lessons learned are captured throughout the project and archived in organizational process assets. A retrospective is one team's improvement event, every iteration.

  29. Card 29

    Change to an approved baseline

    Assess the impact, submit a change request, and let the change control board or the named approver decide; only then implement and update the documents. See integrated change control.

  30. Card 30

    Scope baseline

    The approved scope statement, work breakdown structure (WBS) and WBS dictionary.

02Cards for recall, packages for judgment

A card tells you what management reserve is. It cannot tell you whether the scenario in front of you calls for it, and that call is what a scenario question asks you to make. Flip a dozen cards, then work the same ideas in the PMP practice test, where the notes on each option show the term in use.

Responses to threats and to opportunities have their own page, with the confusable pairs side by side: risk response strategies. To fit the deck into a week, the PMP study plan gives each domain its turn.